The true cost of building my house |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Here, I am going to keep a comprehensive list of
every cost I incure building my house. |
|
|
|
|
|
|
|
|
|
I intend to make it as accurate as possible,
including every cost no mater how small. |
|
|
|
|
|
|
|
|
|
|
It will also include a running tally of labour &
swaps. |
|
|
|
|
|
|
|
|
|
|
|
|
Also, I am counting the total number of days I have
worked on my house |
|
|
|
|
|
|
|
|
|
|
This is so I can work out how much money I would
have made instead of building, so I can add |
|
|
|
|
|
|
|
|
|
it to the cost at the end. When added, it will give
a very accurate, real cost, of building an alternative house. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total costs for major stages: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cost of land: |
$134,518.80 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
Plus associated fees |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cost of project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Pre-construction costs: |
$2,714.53 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
includes council fees |
|
|
|
|
|
|
|
|
|
|
|
|
|
insurances, courses etc |
|
|
|
|
|
days |
w |
359.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
To completion of slab: |
$21,659.11 |
|
<Click for break down of costs> |
|
|
|
w |
300 |
|
|
|
|
|
Plus connection of all services |
|
|
|
|
|
|
oth |
348.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Walls: |
$3,306.56 |
|
<Click for break down of costs> |
|
|
total |
|
1008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Roof and upper rooms: |
$11,962.40 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Services |
$11,735.22 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing off: |
$7,091.50 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping: |
$24.55 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Misc. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Fixings |
$443.01 |
|
|
|
|
|
|
|
|
|
|
|
|
consumables |
$475.83 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
Misc. |
$1,767.20 |
|
|
|
|
|
|
|
|
|
|
|
|
Shack |
$0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Labour: |
$25,595.00 |
|
<Click for break down of costs> |
|
|
|
|
|
|
|
|
|
|
Labour breackdown |
How much time spent on each activity? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total cost: |
$86,774.91 |
|
|
Other costs: |
Cost of stuff ups: |
|
|
|
|
|
|
|
1 'BIG' roll of insulation |
|
|
|
|
|
|
|
|
|
|
|
5 cartons of beer |
|
|
|
|
|
|
|
|
|
|
|
Many home brews |
Tools |
$1,767.20 |
|
|
|
|
|
|
|
|
|
2 bottles of wine |
|
|
|
|
|
|
|
|
|
|
|
|
1 day labour exchange |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Materials |
|
|
|
|
|
|
|
|
|
|
|
|
|
Laborers |
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractors |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Days worked by me |
Days I have worked |
|
|
|
|
|
|
|
|
|
|
|
Total man days (me & labour) |
564.75 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Buying the block of land |
|
|
|
|
|
|
|
|
|
|
|
|
|
Land |
$119,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Tax |
$14,141.60 |
|
|
|
|
|
|
|
|
|
|
|
|
Solicitors fees |
$1,377.20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$134,518.80 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pre-construction costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Blue Mountains Council fees: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Council fees for DA
application |
|
$564.00 |
|
|
|
|
|
|
|
|
|
|
|
|
long service levi |
$200.00 |
|
|
|
|
|
|
|
|
|
|
|
|
inspection notifications |
$297.00 |
|
|
|
|
|
|
|
|
|
|
|
|
road opening permit |
$100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Septic tank approval |
$150.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
total for council: |
$1,311.00 |
|
2003 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Water board approval fee |
$26.00 |
|
2006 |
|
|
|
|
|
|
|
|
|
|
OB course - (compulsory) |
$295.00 |
|
2003 |
|
|
|
|
|
|
|
|
|
|
OB insurance |
$1,082.53 |
|
2006 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Pre-construction costs: |
$2,714.53 |
|
|
|
|
|
|
|
|
|
|
|
|
Note: Most of the above cost were paid around 2003.
Many of the fees & taxes have increased since then. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Building up until completion of slab |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Silt control: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$95.00 |
|
@ $9.5 per bail! |
|
|
|
|
|
|
|
|
|
|
Filter cloth |
$40.80 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$135.80 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Excavation: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Bulk excavation |
$935.00 |
|
10/12/05 |
|
|
|
|
|
|
|
|
|
|
Detail excavation |
$470.00 |
|
1/2/05 |
|
|
|
|
|
|
|
|
|
|
Hire - Jackhammer |
$100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$1,505.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Services: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Getting power on |
$2,300.00 |
|
6/2/06 |
|
|
|
|
|
|
|
|
|
|
Moving temp. power box to house |
...........? |
|
|
|
|
|
|
|
|
|
|
|
|
Septic tanks |
$2,340.00 |
|
6/1/06 |
|
|
|
|
|
|
|
|
|
|
New sewage sceame |
ÉÉ..??? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Under Slab Plumbing |
$5,056.70 |
|
3/5/06 |
|
|
|
|
|
|
|
|
|
|
connecting town water |
|
|
|
|
|
|
|
|
|
|
|
|
|
storm water |
|
|
|
|
|
|
|
|
|
|
|
|
|
under slab |
|
|
|
|
|
|
|
|
|
|
|
|
|
sewerage |
|
|
|
|
|
|
|
|
|
|
|
|
|
Connecting septic tanks |
$500.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total for services: |
$10,196.70 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Slab: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Slab dimensions are: 10m x 10m, with a 540mm step in
the middle, & a retaining wall along two edges which changes in height
from 1000mm too 400mm. |
|
|
|
|
|
|
|
|
Note: |
|
|
|
|
|
|
|
|
|
|
|
|
|
The slab was poured in 3 stages (Retaining wall,
Main slab, & step with top slab. |
|
|
|
|
|
|
|
|
|
|
Doing 3 pours, significantly added to the cost of
the slab in both time and money, but was the easyest way for inexperienced
concreters like ourselves. |
|
|
|
|
|
|
|
|
Dates: 6/2/2006 to 10/3/2006 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Concrete |
$700.00 |
|
Pour 1 |
|
|
|
|
|
|
|
|
|
|
|
$2,541.00 |
|
Pour 2 |
|
|
|
|
|
|
|
|
|
|
|
$1,692.90 |
|
Pour 3 |
|
|
|
|
|
|
|
|
|
|
Steel |
$1,677.03 |
|
|
|
|
|
|
|
|
|
|
|
|
Builders plastic |
$69.28 |
|
|
|
|
|
|
|
|
|
|
|
|
Wood for forming rebate for bricks |
$79.20 |
|
90x45 @3.3/m |
|
|
|
|
|
|
|
|
|
|
In slab heating pipe |
$682.00 |
|
@ $4.6 per m |
|
|
|
|
|
|
|
|
|
|
Termite protection with certification |
$460.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Putty - To fill dents in formwork |
$16.50 |
|
|
|
|
|
|
|
|
|
|
|
|
Cable ties for slab heating hoses |
$3.70 |
|
|
|
|
|
|
|
|
|
|
|
|
Concrete pump hire |
$1,400.00 |
|
For three days |
|
|
|
|
|
|
|
|
|
|
Screed hand |
$500.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
$9,821.61 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Walls up to First floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mud walls: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Builders lime - bag |
$8.70 |
|
(Mitre 10 Blackheath) |
|
|
|
|
|
|
|
|
|
|
Builders lime - bag |
$10.10 |
|
(Bunnings) |
|
|
|
|
|
|
|
|
|
|
Sand & cement - 2 bags |
$11.00 |
|
2 bags (Mome Katoomba) |
2/8/06 |
|
|
|
|
|
|
|
|
|
Sand & cement - 40kg bag |
$8.95 |
|
(Mitre 10 Blackheath) |
21/9/06 |
|
|
|
|
|
|
|
|
|
Sand & cement - 40kg bag |
$8.95 |
|
(Mitre 10 Blackheath) |
26/10/06 |
|
|
|
|
|
|
|
|
|
Cement - 2 bags |
$11.80 |
|
@ 5.9 (Mitre 10 Blackheath) |
|
|
|
|
|
|
|
|
|
|
Cement - 5 bags |
$29.50 |
|
@ 5.9 (Mitre 10 Blackheath) |
|
|
|
|
|
|
|
|
|
|
Cement - 6 bags |
$35.40 |
|
@ 5.9 (Mitre 10 Blackheath) |
|
|
|
|
|
|
|
|
|
|
Cement - 3 bags |
$18.33 |
|
@ 6.11 (Bunnings) |
|
|
|
|
|
|
|
|
|
|
Cement - 5 bags |
$29.50 |
|
@ 5.9 (Mitre 10 Blackheath) |
|
|
|
|
|
|
|
|
|
|
Cement - 3 bags |
$23.00 |
|
@ 5.9 (Mitre 10 Blackheath) |
28/7/06 |
|
|
|
|
|
|
|
|
|
Cement - 5 bags |
$29.50 |
|
(Mitre 10 Blackheath) |
26/10/06 |
|
|
|
|
|
|
|
|
|
Cement - 7 bags |
$37.10 |
|
(Mitre 10 Blackheath) |
2/12/06 |
|
|
|
|
|
|
|
|
|
Cement - 6 bags |
$37.20 |
|
(Mitre 10 Blackheath) |
16/2/07 |
|
|
|
|
|
|
|
|
|
Cement - 10 bags |
$62.00 |
|
(Mitre 10 Blackheath) |
8/3/07 |
|
|
|
|
|
|
|
|
|
Cement - 10 bags |
$62.00 |
|
(Mitre 10 Blackheath) |
16/3/07 |
|
|
|
|
|
|
|
|
|
Cement - 10 bags |
$62.00 |
|
(Mitre 10 Blackheath) |
5/4/07 |
|
|
|
|
|
|
|
|
|
Cement - 10 bags |
$62.00 |
|
(Mitre 10 Blackheath) |
26/4/07 |
|
|
|
|
|
|
|
|
|
Cement - 10 bags |
$65.00 |
|
(Mitre 10 Blackheath) |
7/6/07 |
|
|
|
|
|
|
|
|
|
Cement - 5 bags |
$32.50 |
|
(Mitre 10 Blackheath) |
30/6/07 |
|
|
|
|
|
|
|
|
|
Cement - 5 bags |
$32.50 |
|
(Mitre 10 Blackheath) |
12/7/07 |
|
|
|
|
|
|
|
|
|
Cement - 7 bags |
$45.50 |
|
(Mitre 10 Blackheath) |
28/8/07 |
|
|
|
|
|
|
|
|
|
Cement - 6 bags |
$32.50 |
|
(Mitre 10 Blackheath) |
8/11/07 |
|
|
|
|
|
|
|
|
|
1/2 tonne of sand |
$39.00 |
|
tunks landscape |
17/3/08 |
|
|
|
|
|
|
|
|
|
1/2 tonne of sand |
$39.00 |
|
tunks landscape |
8/4/08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Blackbutt x 10m |
$40.00 |
|
(+ 1 roll of insulation) |
4/8/07 |
|
|
|
|
|
|
|
|
|
8 small railway sleepers |
$80.00 |
|
|
4/4/07 |
|
|
|
|
|
|
|
|
|
Bond Crete - 4lt |
$43.09 |
|
(Mitre 10 Blackheath) |
6/7/06 |
|
|
|
|
|
|
|
|
|
Brick ties |
$33.15 |
|
1 box off 150 (Bunninings) |
30/7/06 |
|
|
|
|
|
|
|
|
|
Damp course |
$22.95 |
|
230mm X 30m |
21/9/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquid Nails (2 tubes) |
$7.70 |
|
Bunnings |
23/8/07 |
|
|
|
|
|
|
|
|
|
Liquid nails X 3 |
$11.50 |
|
Bunnings |
16/9/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$1,062.72 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Windows and Doors |
|
|
|
|
|
|
|
|
|
|
|
|
|
AV515 adhesive |
$41.38 |
|
(3 tubes) |
3/8/06 |
|
|
|
|
|
|
|
|
|
Liquid Nails (2 tubes) |
$9.76 |
|
(Mitre 10 Blackheath) |
24/2/07 |
|
|
|
|
|
|
|
|
|
Liquid Nails (1 tube) |
$4.95 |
|
(Mitre 10 Blackheath) |
21/3/07 |
|
|
|
|
|
|
|
|
|
Epoxy wood filler |
$17.50 |
|
|
6/7/06 |
|
|
|
|
|
|
|
|
|
Bar-D-K timber primer |
$43.40 |
|
|
16/8/06 |
|
|
|
|
|
|
|
|
|
Clear silicon |
$6.85 |
|
Blue Mts Hardware |
26/9/08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Get Door threashholds cut |
$20.00 |
|
|
30/5/06 |
|
|
|
|
|
|
|
|
|
12 x toughened glass |
|
|
5 cartons of beer (Crownies) |
|
|
|
|
|
|
|
|
|
|
|
|
|
massive sheets |
|
|
|
|
|
|
|
|
|
|
6 x toughened glass |
$60.00 |
|
|
|
|
|
|
|
|
|
|
|
|
2 x toughened glass |
$30.00 |
|
|
|
|
|
|
|
|
|
|
|
|
12 x toughened glass |
$10.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Bathroom glass |
|
|
|
17/11/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
External frenc doors |
$2,000.00 |
|
|
17/11/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$2,243.84 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Roof & upper walls: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
First floor and roof timber frme: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Timber - |
|
|
|
|
|
|
|
|
|
|
|
|
|
250x50x24m pine @ $13.84/m |
$549.60 |
|
Blackheath Mitre 10 |
22/9/07 |
|
|
|
|
|
|
|
|
|
200x50x24m pine @ $9.06/m |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
250x45x40m pine @ $13.75/m |
$512.45 |
|
Home hardware Katoomba |
21/9/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
250x50x6m pine @ $13.84/m |
$422.64 |
|
Blackheath Mitre 10 |
10/10/07 |
|
|
|
|
|
|
|
|
|
100x38x120m pine @ $2.83/m |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
250x50x24m pine @ $13.84/m |
$332.16 |
|
Blackheath Mitre 10 |
12/10/07 |
|
|
|
|
|
|
|
|
|
2x Plywood bracing |
$54.18 |
|
Blackheath Mitre 10 |
31/10/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
75x50x120m |
$360.00 |
|
Blackheath Mitre 10 |
18/10/07 |
|
|
|
|
|
|
|
|
|
75x50x36m |
$108.00 |
|
Blackheath Mitre 10 |
14/11/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bolts m12 x 120mm x 60 |
$68.85 |
|
Blackheath Mitre 10 |
19/9/07 |
|
|
|
|
|
|
|
|
|
Roof straping x 60m |
$37.90 |
|
Bunnings |
16/9/07 |
|
|
|
|
|
|
|
|
|
Triplegrips |
$28.00 |
|
Bunnings |
3/9/07 |
|
|
|
|
|
|
|
|
|
clouts |
$6.80 |
|
(Mitre 10 Blackheath) |
8/11/07 |
|
|
|
|
|
|
|
|
|
Pryda flathead nails |
$17.89 |
|
Bunnings |
13/10/07 |
|
|
|
|
|
|
|
|
|
speed bracing - 12m |
$23.52 |
|
Mitre 10 Blackheath |
18/10/07 |
|
|
|
|
|
|
|
|
|
speed bracing - 70m |
$117.60 |
|
Mitre 10 Blackheath |
16/10/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Silver insulation |
$80.00 |
|
for enough for my house |
|
|
|
|
|
|
|
|
|
|
Silver insulation |
$20.00 |
|
2 rolls |
|
|
|
|
|
|
|
|
|
|
19 rolls R3.5 |
|
$150.00 |
|
Ebay |
2/5/10 |
|
|
|
|
|
|
|
|
|
15m roll R3 |
$50.00 |
|
Timber-fix sale |
12/6/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sold extra insulation |
($378.00) |
|
Ebay |
1/4/10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Colour bond roof and first floor cladding: |
|
|
|
|
|
|
|
|
|
|
|
|
Colour bond + all facias etc |
$1,608.63 |
|
Jay Jay building supplies |
29/10/07 |
|
|
|
|
|
|
|
|
|
tin |
$3,802.41 |
|
Jay Jay building supplies |
19/11/07 |
|
|
|
|
|
|
|
|
|
Extra facia |
$74.58 |
|
Jay Jay building supplies |
5/12/07 |
|
|
|
|
|
|
|
|
|
Extra facia |
$74.58 |
|
Jay Jay building supplies |
29/10/07 |
|
|
|
|
|
|
|
|
|
Duraplank weather boards + joiners |
$444.56 |
|
Jay Jay building supplies |
29/10/07 |
|
|
|
|
|
|
|
|
|
27 off 4200x230 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Fibro eave boards |
$181.40 |
|
Jay Jay building supplies |
29/10/07 |
|
|
|
|
|
|
|
|
|
20 off 2400x600 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Touch up spray paint |
$11.50 |
|
Mitre 10 Blackheath |
6/2/08 |
|
|
|
|
|
|
|
|
|
Touch up spray paint |
$10.20 |
|
Bunnings |
17/4/08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Skylight - hall |
$250.00 |
|
trading post |
|
|
|
|
|
|
|
|
|
|
Skylight - stair well |
$105.00 |
|
E-bay |
|
|
|
|
|
|
|
|
|
|
Skylight - stair well |
$220.00 |
|
Timber-fix sale |
12/6/09 |
|
|
|
|
|
|
|
|
|
Skylight - Attic |
$300.00 |
|
E-bay |
|
|
|
|
|
|
|
|
|
|
Skylight - unused |
$300.00 |
|
E-bay |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Roller shutters - Front |
$2,000.00 |
|
|
1/5/09 |
|
|
|
|
|
|
|
|
|
Leaf guard for gutters |
17.95 |
|
thrifty link blackheath |
11/3/11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$11,962.40 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Internal services |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interanl Pumbing |
|
|
|
|
|
|
|
|
|
|
|
|
|
2 toilets |
$400.00 |
|
Ebay |
|
|
|
|
|
|
|
|
|
|
Gas heater |
$200.00 |
|
trading post |
|
|
|
|
|
|
|
|
|
|
Dampflex |
$220.00 |
|
Timber-Fix |
4/6/09 |
|
|
|
|
|
|
|
|
|
Cement - 2 bags - Off white |
$15.90 |
|
(Mitre 10 Blackheath) |
12/6/09 |
|
|
|
|
|
|
|
|
|
Pumber - Matt |
$6,888.88 |
|
|
24/7/09 |
|
|
|
|
|
|
|
|
|
wall plugs |
$5.90 |
|
(Mitre 10 Blackheath) |
28/7/09 |
|
|
|
|
|
|
|
|
|
Pumber - Matt |
2172.88 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Electrical |
|
|
|
|
|
|
|
|
|
|
|
|
|
100m Roll of 1.5mm 3-strand |
$75.00 |
|
|
2/5/09 |
|
|
|
|
|
|
|
|
|
Cross over switch |
$20.00 |
|
|
|
|
|
|
|
|
|
|
|
|
70m Roll of 1.5mm 3-strand |
$20.00 |
|
Garade sale |
13/6/09 |
|
|
|
|
|
|
|
|
|
24m length of 1.5mm 3-strand |
$26.66 |
|
Buckly bros |
1/9/09 |
|
|
|
|
|
|
|
|
|
Smoke detectors x2 |
$99.00 |
|
Buckly bros |
9/9/09 |
|
|
|
|
|
|
|
|
|
Electrician |
$1,591.00 |
|
North Star |
10/9/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$11,735.22 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing off |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing off |
|
|
|
|
|
|
|
|
|
|
|
|
|
Sand paper |
$2.95 |
|
Mitre 10 Blackheath |
30/1/08 |
|
|
|
|
|
|
|
|
|
Sand paper |
$13.40 |
|
Mitre 10 Blackheath |
31/1/08 |
|
|
|
|
|
|
|
|
|
Paint |
$137.00 |
|
Bullaburra paint |
14/2/08 |
|
|
|
|
|
|
|
|
|
Watsons - woodclean |
$15.41 |
|
Bunnings |
27/1/08 |
|
|
|
|
|
|
|
|
|
Watsons - Decking oil |
$162.00 |
|
Bunnings |
27/1/08 |
|
|
|
|
|
|
|
|
|
Touch up paint 1lt |
$32.95 |
|
Mitre 10 Blackheath |
12/5/08 |
|
|
|
|
|
|
|
|
|
twisted wire brush drill attachment |
$13.95 |
|
Mitre 10 Blackheath |
4/6/08 |
|
|
|
|
|
|
|
|
|
wire brush (x3) |
$8.85 |
|
Mitre 10 Blackheath |
4/6/08 |
|
|
|
|
|
|
|
|
|
Pint stripper- Kwick strip 250ml |
$9.45 |
|
Mitre 10 Blackheath |
5/6/08 |
|
|
|
|
|
|
|
|
|
Pint stripper- Accent 500ml |
$9.20 |
|
Mitre 10 Blackheath |
5/6/08 |
|
|
|
|
|
|
|
|
|
Pint stripper- Citristrip 500ml |
$17.95 |
|
Mitre 10 Blackheath |
5/6/08 |
|
|
|
|
|
|
|
|
|
Wrought iron balaustrade |
$3.25 |
|
ebay |
2/8/09 |
|
|
|
|
|
|
|
|
|
cast iron grills |
$7.00 |
|
garadge sale |
24/9/09 |
|
|
|
|
|
|
|
|
|
Antique door knobs |
$9.00 |
|
garadge sale |
5/12/09 |
|
|
|
|
|
|
|
|
|
Gyproc scraps |
$5.00 |
|
garadge sale |
5/12/09 |
|
|
|
|
|
|
|
|
|
Joint cement 4lt |
$16.32 |
|
Mitre 10 Blackheath |
10/8/09 |
|
|
|
|
|
|
|
|
|
Joint cement 20lt |
$42.00 |
|
Timber Fix Lithgow |
31/5/10 |
|
|
|
|
|
|
|
|
|
Gib sound board - 8 sheets |
|
$120.00 |
|
JD |
7/3/10 |
|
|
|
|
|
|
|
|
|
Gib sound board - 3 sheets |
|
$45.00 |
|
JD |
8/6/10 |
|
|
|
|
|
|
|
|
|
Gyproc - 29 sheets |
|
$435.22 |
|
Home hardware Katoomba |
8/3/10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tiling |
|
|
|
|
|
|
|
|
|
|
|
|
|
Tiles lounge/bed/laundry |
$1,540.00 |
|
Tile Mega Mart |
5/1/09 |
|
|
|
|
|
|
|
|
|
Slate sealer |
$95.85 |
|
Mitre 10 Blackheath |
10/8/09 |
|
|
|
|
|
|
|
|
|
Tile adheasive |
$14.85 |
|
Mitre 10 Blackheath |
10/8/09 |
|
|
|
|
|
|
|
|
|
Tile adheasive |
$30.00 |
|
Mitre 10 Blackheath |
30/12/09 |
|
|
|
|
|
|
|
|
|
Grout 2kg |
$7.95 |
|
Mitre 10 Blackheath |
14/8/09 |
|
|
|
|
|
|
|
|
|
Wall grout 10kg |
$23.85 |
|
Bunnings |
18/8/09 |
|
|
|
|
|
|
|
|
|
Slate grout 10kg |
$29.70 |
|
Bunnings |
18/8/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Stairs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Steel stair stringer |
|
38 |
|
Ebay |
25/1/10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kitchen |
|
|
|
|
|
|
|
|
|
|
|
|
|
Draw runners |
$15.00 |
|
Garadge sale |
13/6/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bathroom |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Floor boards |
$3,840.40 |
|
Laws auction |
4/1/10 |
|
|
|
|
|
|
|
|
|
É.. Delivery fee |
$350.00 |
|
|
4/1/10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
$7,091.50 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping |
|
|
|
|
|
|
|
|
|
|
|
|
|
150mm dia Agg. line (4m) |
$1.00 |
|
Garage sale |
|
|
|
|
|
|
|
|
|
|
scutch hammer bits -4 |
$8.70 |
|
Home hardware - Katoomba |
|
|
|
|
|
|
|
|
|
|
scutch hammer bits -8 |
$14.85 |
|
Home hardware - Katoomba |
705/2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
$24.55 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Misc. tools & materials |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fixings: |
|
|
|
|
|
|
|
|
|
|
|
|
|
200 nail plates |
$35.00 |
|
From bunnings (On special) |
|
|
|
|
|
|
|
|
|
|
Gang nails x 3(v large) |
$8.19 |
|
Bunnings |
16/9/07 |
|
|
|
|
|
|
|
|
|
Nails (1kg) |
$7.26 |
|
|
|
|
|
|
|
|
|
|
|
|
Nails (15kg) |
$30.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Screws - various sizes - 1000's |
$40.00 |
|
A carpenter friend |
|
|
|
|
|
|
|
|
|
|
100 bolts |
$48.45 |
|
Bunnings |
25/9/07 |
|
|
|
|
|
|
|
|
|
50 knuckle plates |
$42.50 |
|
Home hardware katoomba |
5/10/07 |
|
|
|
|
|
|
|
|
|
Nails (5kg) |
$13.10 |
|
Home hardware katoomba |
5/10/07 |
|
|
|
|
|
|
|
|
|
Nails (5kg) 75mm |
$24.50 |
|
Blackheath |
31/10/07 |
|
|
|
|
|
|
|
|
|
Nails (5kg) 100mm |
$24.50 |
|
Blackheath |
31/10/07 |
|
|
|
|
|
|
|
|
|
Batten scews - 500 |
$81.41 |
|
Blackheath |
31/10/07 |
|
|
|
|
|
|
|
|
|
35 bolts |
$33.25 |
|
Blackheath |
31/10/07 |
|
|
|
|
|
|
|
|
|
1kg gal clouts |
$8.80 |
|
Blackheath |
3/12/07 |
|
|
|
|
|
|
|
|
|
1kg gal clouts |
$8.80 |
|
Blackheath |
13/12/07 |
|
|
|
|
|
|
|
|
|
Building paper fixings |
$5.00 |
|
Blackheath |
5/12/08 |
|
|
|
|
|
|
|
|
|
Screws zinc 50mm pk100 |
$8.50 |
|
Mitre 10 Blackheath |
31/5/08 |
|
|
|
|
|
|
|
|
|
Screws zinc 75mm pk100 |
$16.50 |
|
Mitre 10 Blackheath |
31/5/08 |
|
|
|
|
|
|
|
|
|
Nails |
$2.00 |
|
Garade sale |
13/6/09 |
|
|
|
|
|
|
|
|
|
Raw plugs - two pkta |
$5.25 |
|
Mitre 10 Blackheath |
24/7/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$443.01 |
|
(on-going) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Consumables |
|
|
|
|
|
|
|
|
|
|
|
|
|
Drill bits |
$13.45 |
|
|
|
|
|
|
|
|
|
|
|
|
Drill bit - 12.5mm |
$19.51 |
|
Mitre 10 Blackheath |
18/9/06 |
|
|
|
|
|
|
|
|
|
Drill bit - long 3/8 |
$24.15 |
|
Mitre 10 Blackheath |
6/7/06 |
|
|
|
|
|
|
|
|
|
Drill bit - 25mm speedbore |
$15.30 |
|
Mitre 10 Blackheath |
6/7/06 |
|
|
|
|
|
|
|
|
|
Drill bit - 32mm speedbore |
$9.50 |
|
Mitre 10 Blackheath |
11/11/06 |
|
|
|
|
|
|
|
|
|
Power bit holder |
$20.96 |
|
Mitre 10 Blackheath |
11/11/06 |
|
|
|
|
|
|
|
|
|
Auger 10mm x 400 long |
$17.95 |
|
Mitre 10 Blackheath |
11/11/06 |
|
|
|
|
|
|
|
|
|
Drill bit 1/8" (x2) |
$2.40 |
|
Mitre 10 Blackheath |
31/5/08 |
|
|
|
|
|
|
|
|
|
Drill bit 7/64" (x2) |
$2.40 |
|
Mitre 10 Blackheath |
31/5/08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cutting discs (steel x10) |
$19.50 |
|
Mitre 10 Blackheath |
|
|
|
|
|
|
|
|
|
|
Angle grinder wheel remover |
$2.00 |
|
|
13/12/06 |
|
|
|
|
|
|
|
|
|
Cutting discs (steel x5) |
$10.00 |
|
Mitre 10 Blackheath |
5/12/07 |
|
|
|
|
|
|
|
|
|
Cutting discs (steel x3) |
$8.85 |
|
Mitre 10 Blackheath |
4/6/08 |
|
|
|
|
|
|
|
|
|
Cutting discs (steel x4) |
$8.36 |
|
Mitre 10 Blackheath |
18/9/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Circular saw blades (X2) |
$29.68 |
|
|
13/12/06 |
|
|
|
|
|
|
|
|
|
Circular saw blade |
$38.00 |
|
|
13/1/07 |
|
|
|
|
|
|
|
|
|
Circular saw blade |
$9.00 |
|
|
12/7/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Electric plainer blades |
$15.95 |
|
Mitre 10 Blackheath |
5/4/07 |
|
|
|
|
|
|
|
|
|
Electric plainer blades x2 |
$31.90 |
|
Mitre 10 Blackheath |
5/12/07 |
|
|
|
|
|
|
|
|
|
Gas cartridges for paslo (X2) |
$17.90 |
|
Mitre 10 Blackheath |
|
|
|
|
|
|
|
|
|
|
É.Tougne and groove bit |
$40.00 |
|
woodwork show Syd |
17/6/07 |
|
|
|
|
|
|
|
|
|
10 wire brushes |
$10.00 |
|
woodwork show Syd |
17/6/07 |
|
|
|
|
|
|
|
|
|
String line chalk |
$6.75 |
|
Mitre 10 Blackheath |
12/7/07 |
|
|
|
|
|
|
|
|
|
sanding belts - 3 |
$15.80 |
|
Home hardware |
26/7/07 |
|
|
|
|
|
|
|
|
|
sanding belts - 7 |
$23.45 |
|
Mitre 10 Blackheath |
30/8/07 |
|
|
|
|
|
|
|
|
|
chainsaw file |
$5.50 |
|
|
30/8/07 |
|
|
|
|
|
|
|
|
|
chalk line |
$4.75 |
|
|
5/10/07 |
|
|
|
|
|
|
|
|
|
chalk |
$6.85 |
|
|
5/10/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PVC priming fluid 500 ml |
$4.62 |
|
Mitre 10 Blackheath |
8/5/08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Router bit |
$23.40 |
|
|
28/6/07 |
|
|
|
|
|
|
|
|
|
Phillips head drill bits |
$8.00 |
|
Garadge sale |
13/6/09 |
|
|
|
|
|
|
|
|
|
Router bit |
$9.95 |
|
(Mitre 10 Blackheath) |
12/6/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$475.83 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tools: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cement mixer |
$400.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Stanley knife |
$22.30 |
|
|
21/9/06 |
|
|
|
|
|
|
|
|
|
small trowel |
$7.95 |
|
|
21/9/06 |
|
|
|
|
|
|
|
|
|
Medium trowel trowel |
$9.25 |
|
|
5/4/07 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Hammer |
$21.00 |
|
|
18/9/06 |
|
|
|
|
|
|
|
|
|
Plum Bob |
$18.95 |
|
|
26/4/07 |
|
|
|
|
|
|
|
|
|
Hand saw |
$10.00 |
|
|
26/4/07 |
|
|
|
|
|
|
|
|
|
Hand saw |
$21.60 |
|
|
12/7/07 |
|
|
|
|
|
|
|
|
|
Hand saw |
$32.95 |
|
Home hardware |
5/10/07 |
|
|
|
|
|
|
|
|
|
Hand saw x 2 |
$20.80 |
|
|
5/12/07 |
|
|
|
|
|
|
|
|
|
String level |
$7.50 |
|
|
|
|
|
|
|
|
|
|
|
|
Water level (Length of clear hose) |
$15.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Getting drill & circular saw fixed |
$70.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Drop saw |
$399.00 |
|
|
17/6/07 |
|
|
|
|
|
|
|
|
|
Router |
$300.00 |
|
|
17/6/07 |
|
|
|
|
|
|
|
|
|
Belt sander |
$150.00 |
|
|
17/6/07 |
|
|
|
|
|
|
|
|
|
Level |
$65.00 |
|
|
17/6/07 |
|
|
|
|
|
|
|
|
|
scutch hammer (home hardware) |
$44.75 |
|
Home hardware |
26/7/07 |
|
|
|
|
|
|
|
|
|
Hand saw (home hardware) |
$32.95 |
|
Home hardware |
26/7/07 |
|
|
|
|
|
|
|
|
|
Adjustable bevel |
$14.40 |
|
Bunnings |
13/10/07 |
|
|
|
|
|
|
|
|
|
hole saw |
$27.50 |
|
|
5/12/07 |
|
|
|
|
|
|
|
|
|
hole saw pin |
$23.05 |
|
|
5/12/07 |
|
|
|
|
|
|
|
|
|
drill bit 1/8 x2 |
$4.80 |
|
|
5/12/07 |
|
|
|
|
|
|
|
|
|
tin snips |
$28.50 |
|
|
5/12/07 |
|
|
|
|
|
|
|
|
|
3 x tape measures |
$9.95 |
|
|
3/12/07 |
|
|
|
|
|
|
|
|
|
Tenching shovel |
$10.00 |
|
|
13/6/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$1,767.20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Misc: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Bottle of wine |
$15.00 |
|
Pay for neighbours power |
|
|
|
|
|
|
|
|
|
|
Besser blocks |
$70.50 |
|
|
|
|
|
|
|
|
|
|
|
|
4 off 5m two by four |
$40.00 |
|
Top & btm plates for shed |
|
|
|
|
|
|
|
|
|
|
Van hire to get glass up mountains |
$100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Tractor hire to move mud bricks |
$50.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Spark plug for generator |
$5.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Fuel for generator |
$5.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Food (& drink) for volunteer's |
$150.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Spark plug for Genny |
$5.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Fuel for chainsaw |
$6.50 |
|
|
|
|
|
|
|
|
|
|
|
|
Fuel for Genny |
$10.00 |
|
(2 x $5) |
|
|
|
|
|
|
|
|
|
|
Getting an extra set of plans stamped by council |
$10.00 |
|
|
|
|
|
|
|
|
|
|
|
|
Spare lock keys cut |
$6.60 |
|
|
24/6/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
$473.60 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Labour & man-hour break down: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Job |
|
|
Days I have worked: |
|
Paid labour: |
|
Volunteer labour: |
Labour exchange |
|
|
Misc. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Shed building / stuffing around |
|
|
6.5 |
|
|
|
|
|
|
15 |
|
|
|
Shack building / stuffing around |
|
|
15.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finding & obtaining materials (since job has
started) |
|
|
17.5 |
|
|
|
|
|
|
|
|
|
|
Transporting & packing materials |
|
|
7 |
|
|
|
|
0.25 |
|
0.25 |
|
|
|
carrying materials |
|
|
3.25 |
|
|
|
|
|
|
|
|
|
|
Rearranging piles of stuff on my block |
|
|
9 |
|
|
|
|
|
|
|
|
|
|
sorting recycled screws, bolts, ect |
|
|
1.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
organizing/research (since job has started) |
|
|
13.25 |
|
|
|
|
|
|
|
|
|
|
organizing/running workers |
|
|
11 |
|
|
|
|
|
|
|
|
|
|
reasearch |
|
|
|
|
|
|
|
|
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Misc jobs (since job has started) |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Cleaning site |
|
|
18.75 |
1 |
|
|
|
1.25 |
|
|
|
|
|
Pottering |
|
|
9 |
|
|
|
|
|
|
|
|
|
|
Upateing this web site when I should be working |
|
|
1.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Services & site prep: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Tree lopping |
|
|
|
|
|
|
|
3 |
|
|
|
|
|
Trees lopping + clearing site |
|
|
3.5 |
|
|
|
|
|
|
|
|
|
|
chainsaw milling |
|
|
0.75 |
|
0.25 |
40.00 |
|
|
|
|
|
|
|
Silt control |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
Bulk excavation |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
Detail excavation |
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
Digging for plumbing |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Digging in Telstra pit |
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
Digging driveway |
|
|
2.25 |
|
0.5 |
60.00 |
|
|
|
|
|
|
|
Sorting rocks |
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
septic tanks |
|
|
5 |
|
|
|
|
|
|
|
|
|
|
Power to site |
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The house: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Slab |
|
|
|
|
|
|
|
|
|
|
|
|
|
Concrete slab |
|
|
17.5 |
|
|
|
|
|
|
|
|
|
|
Slab |
|
|
|
|
2 |
240.00 |
|
|
|
|
|
|
|
Slab formwork |
|
|
|
|
|
|
|
2 |
|
|
|
|
|
Concrete pour |
|
|
|
|
0.5 |
65.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ground floor walls |
|
|
|
|
|
|
|
|
|
|
|
|
|
Moving bricks |
|
|
1 |
|
3.25 |
410.00 |
|
|
|
|
|
|
|
Digging & sifting mortar |
|
|
2.5 |
|
5.25 |
668.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mud walls |
|
|
|
1 |
38.75 |
4,682.00 |
|
3.5 |
|
|
|
|
|
Laying bricks |
|
|
23 |
|
|
|
|
|
|
|
|
|
|
Sorting rocks for wall |
|
|
|
|
1.75 |
216.00 |
|
|
|
|
|
|
|
Laying rock in mud walls |
|
|
|
|
8 |
1,000.00 |
|
|
|
|
|
|
|
Poured earth molds |
|
|
3 |
|
1.5 |
180.00 |
|
|
|
|
|
|
|
Formed earth walls |
|
|
3 |
|
4.75 |
570.00 |
|
2 |
|
|
|
|
|
top plates on mud walls |
|
|
3.75 |
|
2.25 |
270.00 |
|
|
|
|
|
|
|
Bagging |
|
|
0.5 |
|
2.5 |
342.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Columns |
|
|
8.75 |
|
|
|
|
|
|
|
|
|
|
Beams |
|
|
9.25 |
|
|
|
|
|
|
|
|
|
|
Columns & Beams |
|
|
|
|
6.25 |
768.00 |
|
|
|
|
|
|
|
Cutting notches in columns |
|
|
|
|
|
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing timbers (sanding etc) |
|
|
1 |
|
3.25 |
300.00 |
|
|
|
|
|
|
|
Sunroom framing |
|
|
2 |
|
2 |
356.00 |
|
|
|
|
|
|
|
windows in internal mud wall 1st floor |
|
|
1 |
1 |
0.75 |
120.00 |
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
First floor and roof framing |
|
|
|
|
|
|
|
|
|
|
|
|
|
Profesional carpenter |
|
|
|
|
5 |
2,628.00 |
|
|
|
|
|
|
|
É.. & appretice |
|
|
|
|
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
De-nail reused timbers |
|
|
3 |
|
1.5 |
216.00 |
|
0.25 |
|
|
|
|
|
Cutting slabs |
|
|
0.75 |
|
4.75 |
570.00 |
|
|
|
|
|
|
|
Prep rafters (Cut/nail plate) |
|
|
0.5 |
|
0.25 |
36.00 |
|
|
|
|
|
|
|
Painting |
|
|
|
|
1.25 |
156.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nailing down floor joists |
|
|
0.25 |
|
4 |
708.00 |
|
|
|
|
|
|
|
1st floor sub flooring |
|
|
1 |
|
1.75 |
216.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Putting up rafters |
|
|
3.75 |
|
3.5 |
494.00 |
|
|
|
|
|
|
|
Inserting blockouts btwn rafters |
|
|
2.5 |
|
1.75 |
252.00 |
|
|
|
|
|
|
|
Bolting together rafters |
|
|
|
|
1.5 |
216.00 |
|
|
|
|
|
|
|
triple griping joists and rafters |
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
stud walls |
|
|
4.25 |
|
9 |
1,012.00 |
|
|
|
|
|
|
|
dormers side walls |
|
|
4.25 |
|
3 |
510.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Roof |
|
|
|
|
|
|
|
|
|
|
|
|
|
Making scaff |
|
|
|
|
0.5 |
72.00 |
|
|
|
|
|
|
|
Roof bracing |
|
|
|
|
1 |
144.00 |
|
|
|
|
|
|
|
Battens |
|
|
2 |
|
5 |
520.00 |
|
|
|
|
|
|
|
|
|
|
|
|
1 |
480.00 |
|
|
|
|
|
|
|
steel fascia boards/gutter |
|
|
4.5 |
1 |
4.25 |
520.00 |
|
|
|
|
|
|
|
ColourBond roof |
|
|
8.25 |
|
5.25 |
729.00 |
|
|
|
|
|
|
|
Install skylights |
|
|
4.75 |
0.5 |
1.75 |
290.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
External Cladding |
|
|
|
|
|
|
|
|
|
|
|
|
|
paper/flashing |
|
|
0.75 |
|
|
|
|
0.25 |
|
|
|
|
|
Fascia boards - front |
|
|
2.25 |
|
2 |
320.00 |
|
|
|
|
|
|
|
Tin - back |
|
|
2 |
|
1.25 |
200.00 |
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
dormers fascia |
|
|
2 |
|
0.5 |
80.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
External windows and doors |
|
|
|
|
|
|
|
|
|
|
|
|
|
Making window/door frames |
|
|
8.25 |
|
1.25 |
200.00 |
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ground floor Door & widow frames |
|
|
13 |
|
7.25 |
870.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Installing front ceader windows |
|
|
0.25 |
|
0.5 |
80.00 |
|
|
|
|
|
|
|
1st floor - Door & window frames -back |
|
|
5 |
|
2 |
320.00 |
|
|
|
|
|
|
|
Installing glass in fixed windows |
|
|
1 |
|
0.75 |
135.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Installing windows |
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
Hanging external doors |
|
|
1.75 |
|
1.75 |
270.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing off external |
|
|
|
|
|
|
|
|
|
|
|
|
|
Eave framing |
|
|
0.75 |
|
2.25 |
360.00 |
|
|
|
|
|
|
|
Eave boards |
|
|
3 |
|
3 |
440.00 |
|
|
|
|
|
|
|
beading between eavs and fascia |
|
|
0.25 |
1 |
0.25 |
20.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sanding external beams |
|
|
1.25 |
|
3 |
432.00 |
|
|
|
|
|
|
|
Painting |
|
|
1 |
|
1.5 |
216.00 |
|
|
|
|
|
|
|
oilling external timber |
|
|
0.25 |
|
|
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
finishing of front windows |
|
|
0.25 |
|
0.25 |
40.00 |
|
|
|
|
|
|
|
window boarders |
|
|
0.5 |
1.5 |
|
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Front door awning |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Internal (non-structural) stud walls |
|
|
|
|
|
|
|
|
|
|
|
|
|
stud walls |
|
|
1.5 |
|
2.75 |
696.00 |
1 |
|
|
|
|
|
|
Attic floors |
|
|
3 |
|
0.5 |
72.00 |
1.5 |
|
|
|
|
|
|
Attic claddings |
|
|
3.5 |
|
1 |
120.00 |
|
0.5 |
|
|
|
|
|
Attic internal windows |
|
|
1.25 |
|
|
|
|
0.25 |
|
|
|
|
|
framing up laundry |
|
|
0.25 |
|
0.25 |
40.00 |
|
|
|
|
|
|
|
Installing door jframes |
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
Hanging door |
|
|
|
1 |
|
|
|
|
|
|
|
|
|
bagging first floor walls |
|
|
0.75 |
|
|
|
|
0.75 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finishing off internal |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cleaning mud of rocks in wall |
|
|
1 |
|
1 |
144.00 |
|
2.5 |
|
|
|
|
|
Finishing internal timbers |
|
|
|
|
0.5 |
72.00 |
|
|
|
|
|
|
|
Cleaning glass |
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cupboards/ |
|
|
1 |
|
|
|
|
1 |
|
|
|
|
|
Bedroom Storage areas |
|
|
6.5 |
|
|
|
|
3.25 |
|
0.75 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
battens and trim for gyproc |
|
|
|
5 |
|
|
|
|
0.5 |
|
|
|
|
|
Insulation |
|
|
6 |
|
0.25 |
40.00 |
|
|
|
|
|
|
|
Gyproc installing |
|
|
8.75 |
|
|
|
|
2.5 |
|
|
|
|
|
Gyproc plastering |
|
|
3.5 |
|
|
|
|
2.5 |
|
1 |
|
|
|
Beeding attic |
|
|
|
1.25 |
|
|
|
|
0.75 |
|
1 |
|
|
|
painting attic |
|
|
|
0.25 |
|
|
|
|
|
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Painting |
|
|
|
1 |
|
|
|
2 |
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Stacking floor boards |
|
|
0.5 |
|
|
|
|
0.75 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Plumbing |
|
|
|
|
|
|
|
|
|
|
|
|
|
General helping |
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
chasing pipes & re-mudding |
|
|
2.75 |
|
|
|
|
|
|
|
|
|
|
Slab under hot water heater |
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
sewer scheme - cleaning |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
sewer scheme - digging |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Electrical |
|
|
|
|
|
|
|
|
|
|
|
|
|
Running wirers |
|
|
6.5 |
|
0.25 |
36.00 |
|
|
|
|
|
|
|
Instaling lights/power points |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Running AG6 & Cat5e |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
sorting/fixing lead lights |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gas |
|
|
|
|
|
|
|
|
|
|
|
|
|
Digging |
|
|
1.25 |
|
|
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kitchen |
|
|
|
|
|
|
|
|
|
|
|
|
|
Kitchen benchs |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Wall cupboard area |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bathroom(s)/laundry |
|
|
|
|
|
|
|
|
|
|
|
|
|
Helping plumber |
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.75 |
|
|
|
|
1.75 |
|
|
|
|
|
Sealing |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Fibro |
|
|
3 |
|
|
|
|
2 |
|
|
|
|
|
Cleaning used slate tiles |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Laying tiles |
|
|
4 |
|
|
|
|
|
|
|
|
|
|
grouting |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
Laundry cupboard |
|
|
1.75 |
|
|
|
|
|
|
|
|
|
|
mosaic |
|
|
4.5 |
|
|
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Landscaping |
|
|
|
|
|
|
|
|
|
|
|
|
|
Retaining walls side of house |
|
|
2 |
|
1.75 |
210.00 |
|
|
|
|
|
|
|
Garden retaining walls |
|
|
3.75 |
|
0.25 |
30.00 |
|
2.25 |
|
|
|
|
|
Agg. Drain around house |
|
|
|
|
0.75 |
96.00 |
|
|
|
|
|
|
|
Garden building |
|
|
2 |
|
|
|
|
2.5 |
|
|
|
|
|
tire retaining walls |
|
|
2 |
|
|
|
|
|
|
|
|
|
|
Other |
|
|
0.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Days I have worked |
|
Paid labour |
|
Volunteer |
|
|
|
|
|
Total: |
|
|
394.25 |
|
181.25 |
$25,595.00 |
|
44.5 |
|
20.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Days lost by: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(Note: That I only work Wendsday to Friday on my
house, So all these |
|
|
|
|
|
|
|
|
|
|
lost days are within a 3 day week) |
|
|
|
|
|
|
|
|
|
|
|
|
|
_2006 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Rain !!!!! |
|
|
53 |
|
|
|
|
|
|
|
|
|
|
Sick - mostly due to hay fever |
|
|
31 |
|
|
|
|
|
|
|
|
|
|
Damaged shoulder |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Car sagaÉ |
|
|
36 |
|
|
|
|
|
|
|
|
|
|
Car breaking down in Adelaide....Going to Adelaide
to pick |
|
|
|
|
|
|
|
|
|
|
up stuff....looking for new car....buying new
car....new car |
|
|
|
|
|
|
|
|
|
|
breaking down....Getting money back.........looking
for |
|
|
|
|
|
|
|
|
|
|
|
another car....buying another car....and then that
one breaking |
|
|
|
|
|
|
|
|
|
|
down! Arrgh!... Fixing it etc etc |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
To tiered (Bludging) |
|
|
5 |
|
|
|
|
|
|
|
|
|
|
Holidays |
|
|
11 |
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
139 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
_2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
rain |
|
|
26 |
|
|
|
|
|
|
|
|
|
|
injury |
|
|
2.5 |
|
|
|
|
|
|
|
|
|
|
Hayfever |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Car problems |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
Hospital procedure |
|
|
1 |
|
|
|
|
|
|
|
|
|
|
To tiered (Bludging) |
|
|
9 |
|
|
|
|
|
|
|
|
|
|
Holidays |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Waiting for direction from mud expert |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
48.5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
_2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Holidays |
|
|
22 |
|
|
|
|
|
|
|
|
|
|
People visiting |
|
|
25 |
|
|
|
|
|
|
|
|
|
|
To tiered (Bludging) |
|
|
10 |
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
57 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
_2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Holidays |
|
|
19 |
|
|
|
|
|
|
|
|
|
|
Helping Cindi |
|
|
21.5 |
|
|
|
|
|
|
|
|
|
|
Education |
|
|
48.5 |
|
|
|
|
|
|
|
|
|
|
To tiered (Bludging) |
|
|
4.5 |
|
|
|
|
|
|
|
|
|
|
sick |
|
|
1.75 |
|
|
|
|
|
|
|
|
|
|
Hayfever |
|
|
3.25 |
|
|
|
|
|
|
|
|
|
|
gone climbing instead |
|
|
2.5 |
|
|
|
|
|
|
|
|
|
|
Giving people tours of house |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
104 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
_2010 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Holidays |
|
|
3 |
|
|
|
|
|
|
|
|
|
|
Medical related |
|
|
|
4.75 |
|
|
|
|
|
|
|
|
|
|
helping cindi |
|
|
|
10.25 |
|
|
|
|
|
|
|
|
|
|
To tiered (Bludging) |
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
gone climbing instead |
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
Gardening (procastinating) |
|
|
|
0.25 |
|
|
|
|
|
|
|
|
|
|
Council cleanups! |
|
|
|
1 |
|
|
|
|
|
|
|
|
|
|
Mega Party stuff |
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
making arm / arm packaging |
|
|
|
1.25 |
|
|
|
|
|
|
|
|
|
|
Giving people tours of house |
|
|
2.25 |
|
|
|
|
|
|
|
|
|
|
Houshold choirs |
|
|
|
1.75 |
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
29 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|