Bulk Excavation
 
 
Saturday - 17th December 2005
 
     
 

When we chopped down the trees, we left about 1.5m of the stump sticking out, to make it easy for the excavator to rip out.

We found out later that the smaller 2 tonne excavater Peter Saxby was gonna use wouldn't be able to handle them. So we had to get Peter Corny in with his bigger machine.

This worked out OK in the end, as I could use his bigger machine to dig the pits for the septic tanks.

 

 

Stump ends (Using Ant for scale)  
Ripping out one of the medium stumps.
   
 
Moving around the bigger stumps with most of the roots removed.
   
 
 
 

 

 
   
 
   
 
Stacking the logs
Digging hole for my pumpouts
Scraping away