01/07/2008
       
           
 
   
 
           
 
11/06/2008
   
12/06/2008
 
           
 
   
 
           
 
07/06/2008
   
29/05/2008
 
           
 
   
 
           
 
19/12/2007
   
19/12/2007
 
           
 

 
 
           
 
20/10/2007
   
19/11/2007
 
 

   
 

12/10/2007

Now with a part of my rear rafters up, I can begin to get a feel for what the house will look like.

           
 

 
           
 
28/9/2007
Rafters complete
 
29/9/2007
Sub-floor complete
5/10/2007
My first internal stud walls
 
   
27/9/2007
   

20/9/2007

This shows my almost completed rafters

   
   
 

26/6/2007
 
         

15/6/2007

I finally have a back yard
   
12/12/2006
   
12/11/2006
After recording 50 rainy days since Feb, The rain has finally stopped and the walls are jumping up!
   
12/9/2006
Due to rain, progress has been slow....
   
25/5/2006
   
25/5/2006
First course of mud bricks!
In the forground are vertical poles to run string lines.
   
15/3/2006
Third pour done. And now the slab is complete.
   
27/2/2006
The site quickly becomes a mess!
   
25/2/2006
Shot showing the freshly poured slab
   

25/2/2006
About to start the second pour

   
24/2/2006
Getting ready to do the second pour
   
23/2/2006
After pour 1
Detail excavation after installing the plumbing
   
So it begins